Core details:

Project: Fowlers Rd to Fairwater Dr Link – Electrical Lighting Package

Project Location: Illawarra Region – Dapto NSW

Project Value ($AUD): $1.1m

Project Length (Weeks): 15 Weeks

ARA Divisions Involved: ARA Electrical

Project Manager Involved: Rhys Ayuso – Construction Manager

Client Associated: Abergeldie Complex Infrastructure




About the project:

Diverting existing power lines and ensure we make way for new infrastructure and roads is no easy feat. The Electrical Reticulation works at Fowlers Road in Dapto help provide public lighting in-line with current requirements for the new Fowlers Road to Fairwater Drive Link.

The work completed shows significant capability in ARA Electrical’s live low-voltage work, with qualified in-house Linemen and Cable Joiners operating with significant caution and best safe work practice alongside live major roads, ensuring the major link could enable commuters to pass safely.