Core details:

Project: Arncliffe Chamber Substation

Project Location: Princess Highway, Arncliffe NSW

Project Value ($AUD): $900K

Project Length (Weeks): 16 Weeks

ARA Divisions Involved: ARA Electrical

Client Associated: Richard Crookes




About the project:

The goal for the Richard Crookes project was to establish the commissioning of the chamber substation in a timely manner, and remove generators which were running the site. This consisted of the establishment of three Chamber Substations & six Streetlights, all containing High and Low Voltage components, such as boards and switchgear.

Challenges of the project:

Some of the significant challenges the ARA Electrical team had to face were the excavation around existing services for the installation of conduits which were located nearby NBN infrastructure cable which powers the Sydney Airport Network.